PROJECTS COMPLETED

PROJECTS COMPLETED

  • 2016UPGRADE OF PLC SYSTEMS FOR SEA WATER

    siemens
    Upgrade of PLC systems for sea water intake bar and band screening system Phase-2 at Shoaiba Desalination Plant
    LOCATION: Shoaiba – Saudi Arabia
    END USER: Saline Water Conversion Company (SWCC)
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2016
  • 2016UPGRADE OF 10 PLC SYSTEMS FOR BALL CLEANING

    siemens
    Upgrade of 10 PLC systems for Ball Cleaning System – Phase-2 at Shoaiba Desalination Plant
    LOCATION: Shoaiba – Saudi Arabia
    END USER: Saline Water Conversion Company (SWCC)
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2016
  • 2015UPGRADE OF PLC SYSTEMS FOR SEA WATER INTAKE BAR

    siemens
    Upgrade of PLC systems for sea water intake bar and band screening system Phase-1 at Shoaiba Desalination Plant
    LOCATION: Shoaiba – Saudi Arabia
    END USER: Saline Water Conversion Company (SWCC)
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2015
  • 2015UPGRADE OF 10 PLC SYSTEMS FOR BALL CLEANING SYSTEM

    siemens
    Upgrade of 10 PLC systems for Ball Cleaning System – Phase-1 at Shoaiba Desalination Plant
    LOCATION: Shoaiba – Saudi Arabia
    END USER: Saline Water Conversion Company (SWCC)
    SYSTEM: SIEMENS SIMATIC S7-1500, SIEMENS SIMATIC HMI
    YEAR: 2015
  • 2015ENGINEERING & SUPPLY OF ABTS

    siemens
    Engineering & supply of ABTS for 13.8KV Substation at Umm Ul Qura University
    LOCATION: Makkah– Saudi Arabia
    END USER: Saudi Electricity Company)
    SYSTEM: SIEMENS SIMATIC S7-300
    YEAR: 2015
  • 2015CENTRALIZED CONTROL & MONITORING SYSTEM FOR MV NETWORK

    siemens
    Engineering, design, supply, testing and commissioning of centralized control & monitoring system for MV Network of King Abdul Aziz International Airport
    LOCATION: Jeddah– Saudi Arabia
    END USER: General Authority of Civil Aviation
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2015
  • 2015ENGINEERING & SUPPLY OF ANNUNCIATION SYSTEM

    siemens
    Engineering & supply of Annunciation System for 380KV Thuwal-2 Substation
    LOCATION: Jeddah– Saudi Arabia
    END USER: General Authority of Civil Aviation
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2015
  • 2015ENGINEERING, DESIGN & SUPPLY OF RO PLANT

    siemens
    Engineering, design & supply of 5000 m3/day RO plant at Ministry of Defense & Aviation Training School
    LOCATION: Jeddah– Saudi Arabia
    END USER: Ministry of Defense & Aviation
    SYSTEM: SIEMENS SIMATIC S7-400H, SIEMENS SIMATIC HMI
    YEAR: 2015
  • 2014CONTROL SYSTEM FOR DIESEL ENGINE

    siemens
    Engineering, design, supply, testing and commissioning of control system for diesel engine fire pumps
    LOCATION: Jeddah– Saudi Arabia
    END USER: SWCC Jeddah
    SYSTEM: SIEMENS SIRIUS
    YEAR: 2014
  • 2014CHLORINATION SYSTEM

    siemens
    Engineering and supply, testing and commissioning of chlorination system for Riyadh Strategic Tanks
    LOCATION: Riyadh– Saudi Arabia
    END USER: National Water Company
    SYSTEM: SIEMENS SIMATIC S7-1200, SIEMENS SIMATIC HMI
    YEAR: 2014
  • 2014PUMPING STATION

    siemens
    Engineering, testing & commissioning of pumping station @ MINA - MAKKAH
    LOCATION: Mina Makkah – Saudi Arabia
    END USER: Ministry of Interior
    SYSTEM: SIEMENS SIMATIC S7-1200
    YEAR: 2014
  • 2014POWER FACTOR CORRECTION SYSTEM

    vendor_shneider
    Engineering & commissioning of PLC based power factor correction system @ Al-Majarda SS
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SCHNEIDER-ELECTRIC MODICON M340
    YEAR: 2014
  • 2014MBR PLANT

    vendor_shneider
    Engineering, testing & commissioning of 2500 m3/day MBR plant @ Raabigh Power Plant – Raabigh
    LOCATION: Raabigh – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SCHNEIDER-ELECTRIC QUANTUM; SIEMENS SIMATIC HMI
    YEAR: 2014
  • 2014CENTRALIZED CONTROL & MONITORING SYSTEM

    siemens
    Engineering, design, supply, testing and commissioning of centralized control & monitoring system for MV Network
    LOCATION: Jeddah – Saudi Arabia
    END USER: Bazel Al-Khair
    SYSTEM: SIEMENS SIMATIC S7-300; SIEMENS SIMATIC HMI
    YEAR: 2014
  • 2014CONTROL SYSTEM FOR LUBE OIL BLENDING PLANT

    siemens
    Complete control system including engineering, design, supply, testing and commissioning of lube oil blending plant
    LOCATION: Jeddah – Saudi Arabia
    END USER: PetroLife
    SYSTEM: SIEMENS SIMATIC S7-300; SIEMENS SIMATIC HMI
    YEAR: 2014
  • 2013GREY WATER TREATMENT SYSTEM

    siemens
    Supply, design, engineering & commissioning of Grey Water Treatment PLC system
    LOCATION: Jeddah – Saudi Arabia
    END USER: Mars Inc.
    SYSTEM: SIEMENS S7-1200
    YEAR: 2013
  • 2013SUBSTATION ANNUNCIATION SYSTEM

    siemens
    Engineering & commissioning of substation annunciation system at Madinah East S/S
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SIEMENS S7-400H
    YEAR: 2013
  • 2013SOOT BLOWER SYSTEM FOR BOILER

    allen-bradley
    Commissioning of Soot Blower System for boiler-9 and boiler-12
    LOCATION: Jeddah – Saudi Arabia
    END USER: SWCC Jeddah
    SYSTEM: ALLEN BRADLEY ML1500
    YEAR: 2013
  • 2013AUTOMATIC CAPACITANCE CONTROL SYSTEM

    vendor_shneider
    Engineering & commissioning of 13.8KV automatic capacitance control system at PSC substation Makkah
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SCHNEIDER-ELECTRIC MODICON M340
    YEAR: 2013
  • 2013RO PLC SYSTEM

    siemens
    Engineering & commissioning of 500 m3 RO PLC system
    LOCATION: Jeddah – Saudi Arabia
    END USER: Wetico
    SYSTEM: SIEMENS S7-1200
    YEAR: 2013
  • 2013POWER FACTOR CORRECTION SYSTEM

    siemens
    Engineering & commissioning of PLC based power factor correction system stage-1 (7 substations)
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SIEMENS SIMATIC S7-300 ; SIEMENS SIMATIC HMI
    YEAR: 2013
  • 2013POWER FACTOR CORRECTION SYSTEM

    siemens
    Engineering & commissioning of PLC based power factor correction system stage-2 (23 substations)
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co.
    SYSTEM: SIEMENS SIMATIC S7-300 ; SIEMENS SIMATIC HMI
    YEAR: 2013
  • 2013SOLVENT RECOVERY SYSTEM

    siemens
    Engineering & commissioning of solvent recovery system
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Modern Packaging Co.
    SYSTEM: SIMATIC S7-400; SIEMENS SIMATIC WINCC
    YEAR: 2013
  • 2013AUTOMATION SYSTEM

    siemens
    Supply & engineering of automation system for Riyadh strategic tanks
    LOCATION: Saudi Arabia
    END USER: Wetico
    SYSTEM: ALLEN BRADLEY ML1500
    YEAR: 2013
  • 2012RO PLANT

    siemens
    Complete control scheme development, engineering, design, testing and commissioning of 1000 m3/day RO Plant
    LOCATION: Jeddah – Saudi Arabia
    END USER: Al-Khair Contracting
    SYSTEM: SIEMENS S7-300; SIEMENS SIMATIC HMI
    YEAR: 2012
  • 2012ADDITION OF PROCESS INSTRUMENTS INTO GAS TURBINE CONTROL SYSTEMS

    GE imagination at work
    Addition of process instruments into gas turbine control systems at Saudi ARAMCO Jeddah Refinery
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Aramco Jeddah Refinery
    SYSTEM: GE MARK-V
    YEAR: 2012
  • 2012COMPLETE AUTOMATION SYSTEM FOR RO PLANT

    siemens
    Supply, design, engineering & commissioning of complete automation system for 2 x 1000 m3/day RO plant
    LOCATION: Jeddah – Saudi Arabia
    END USER: Al-Khair Contracting
    SYSTEM: SIEMENS SIMATIC S7-1200; SIEMENS SIMATIC HMI
    YEAR: 2012
  • 2012UPGRADE OF ABB PROCONTIC CS31 PLC SYSTEM

    siemens
    Upgrade of ABB procontic CS31 PLC system for 250 m/min flexo machine
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Modern Packaging Co.
    SYSTEM: SIEMENS SIMATIC S7-300; SIEMENS SIMATIC WINCC
    YEAR: 2012
  • 2012AUTOMATIC CAPACITANCE CONTROL SYSTEM

    vendor_shneider
    Engineering & commissioning of 13.8KV and 33KV automatic capacitance control system at Bisha South S/S
    LOCATION: Jeddah – Saudi Arabia
    END USER: Saudi Electricity Co. .
    SYSTEM: SCHNEIDER-ELECTRIC MODICON M340
    YEAR: 2012